[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1114903":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1114903,788,1,"单选题","工程师应当在接到延期开工申请后的()内以书面形式答复承包人。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","24小时",false,{"key":16,"text":17,"correct":18},"B","48小时",true,{"key":20,"text":21,"correct":14},"C","3天",{"key":23,"text":24,"correct":14},"D","5天","2020版教材P111页 工程师应当在接到延期开工申请后的48小时内以书面形式答复承包人。工程师在接到延期开工申请后48小时内不答复，视为同意承包人要求，工期相应顺延。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]