[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1114901":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1114901,788,1,"单选题","甲建筑公司为了中标借用了乙建筑公司的资质。2010年12月，其所承建的工程竣工验收合格。此后甲因工程款纠纷起诉到法院，建设单位请求认定合同无效。关于本案，说法正确的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","由于工程竣工验收合格，人民法院应当认定合同有效",false,{"key":16,"text":17,"correct":18},"B","由于工程竣工验收合格，甲有权请求参照合同约定支付工程款",true,{"key":20,"text":21,"correct":14},"C","由于合同无效，业主有权拒绝支付全部工程款",{"key":23,"text":24,"correct":14},"D","由于合同无效，人民法院有权收缴甲公司的全部工程款","2020版教材P121 《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释》规定，建设工程施工合同无效，但建设工程经竣工验收合格，承包人请求参照合同约定支付工程价款的，应予支持。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]