[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1114891":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1114891,788,1,"单选题","以下不属于发包人请求解除合同的条件是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","不履行合同约定的协助义务的",true,{"key":16,"text":17,"correct":18},"B","将承包的建设工程非法转包、违法分包的",false,{"key":20,"text":21,"correct":18},"C","已经完成的建设工程质量不合格，并拒绝修复的",{"key":23,"text":24,"correct":18},"D","明确表示或者以行为表明不履行合同主要义务的","2020版教材P125页 承包人具有下列情形之一，发包人请求解除建设工程施工合同的，应予支持：(1)明确表示或者以行为表明不履行合同主要义务的；(2)合同约定的期限内没有完工，且在发包人催告的合理期限内仍未完工的；(3)已经完成的建设工程质量不合格，并拒绝修复的；(4)将承包的建设工程非法转包、违法分包的。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]