[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1114888":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1114888,788,1,"单选题","2009年3月22日，甲建设单位与乙施工单位签订了一份承包合同，合同中约定乙施工单位工程项目必须于2010年9月28日前完工，如拖期罚款为5000元\u002Fd，后来由于施工企业的原因导致工程到期未能完工。根据我国《合同法》的规定，乙施工企业应()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","支付拖期罚款后中止履行合同",false,{"key":16,"text":17,"correct":18},"B","支付拖期罚款后继续履行合同",true,{"key":20,"text":21,"correct":14},"C","支付拖期罚款后终止履行合同",{"key":23,"text":24,"correct":14},"D","选择支付拖期罚款或继续履行合同","2020版教材P126 当事人一方不履行合同义务或者履行合同义务不符合约定的，应当承担继续履行、采取补救措施或者赔偿损失等违约责任。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]