[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1114857":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1114857,788,1,"单选题","承包人与材料供应商合同约定买卖钢材500吨，由于施工内容的调整变化，发包人通知承包人可能要改变交货数量，但一直没有明确具体交货数额。交货期到达，供应商将500吨钢筋交付承包人，承包人拒绝接受，理由是合同已协议变更，则正确的说法是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","供应商应承担由此给承包人造成的损失",false,{"key":16,"text":17,"correct":14},"B","承包人可根据实际情况部分接受货物",{"key":19,"text":20,"correct":14},"C","由于双方已变更合同，乙应暂停送货",{"key":22,"text":23,"correct":24},"D","承包人拒绝接受，应承担违约责任",true,"2020版教材P122 当事人对合同变更的内容约定不明确的，推定为未变更，本题中双方对变更合同的交货数量属于约定不明确，应推定为未变更，供应商按照原合同约定执行合同，承包人拒绝接受，应承担违约责任。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]