[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1114837":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1114837,788,1,"单选题","建设工程在开工阶段不能顺延工期的情况是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","承包人因施工机械不能及时到位，在开工前7天以书面形式向工程师提出延期开工，工程师在48小时内未作书面答复",false,{"key":16,"text":17,"correct":18},"B","承包人因工人不能按时到岗开工，后以书面形式向工程师提出延期施工",true,{"key":20,"text":21,"correct":14},"C","因设计进度拖延，工程师书面通知承包人延期开工",{"key":23,"text":24,"correct":14},"D","因施工场地未达到开工要求，工程师书面通知承包人延期开工","2020版教材P111页 承包人应当按照协议书约定的开工日期开工。承包人不能按时开工，应当不迟于协议书约定的开工日期前7天，以书面形式向工程师（指本工程监理单位委派的总监理工程师或发包人指定的履行本合同的代表）提出延期开工的理由和要求。工程师应当在接到延期开工申请后的48小时内以书面形式答复承包人。工程师在接到延期开工申请后48小时内不答复，视为同意承包人要求，工期相应顺延。选项A属于该情况，选项B没能在开工前7天以书面形式提出延期开工，不能顺延工期；选项C、D属于发包人原因推迟开工，因发包人原因不能按照协议书约定的开工日期开工，工程师应以书面形式通知承包人，推迟开工日期。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]