[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1114757":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1114757,788,1,"单选题","某建设工程的承包人将工程进行了转包，导致实际施工人的工程款被拖欠。根据有关司法解释的规定，下列说法错误的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","实际施工人只能以发包人为被告主张权利",true,{"key":16,"text":17,"correct":18},"B","实际施工人可以以转包人为被告起诉",false,{"key":20,"text":21,"correct":18},"C","人民法院可以追加转包人为本案当事人",{"key":23,"text":24,"correct":18},"D","发包人只在欠付工程价款范围内对实施工人承担责任","2020版教材P100页 《建筑法》规定，建筑工程总承包单位按照总承包合同的约定对建设单位负责；分包单位按照分包合同的约定对总承包单位负责。总承包单位和分包单位就分包工程对建设单位承担连带责任。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]