[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1114754":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1114754,788,1,"单选题","甲公司投标中标承包了某开发商的写字楼工程施工任务，下列做法中合法的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","甲公司将部分劳务作业任务分包给乙公司",true,{"key":16,"text":17,"correct":18},"B","开发方指定丙公司为安装工程的分包人",false,{"key":20,"text":21,"correct":18},"C","甲公司将该工程施工任务切块分包给了不同承包商",{"key":23,"text":24,"correct":18},"D","丙公司与开发方签订工程承包合同","2020版教材P97页 《建筑法》规定，建筑工程总承包单位可以将承包工程中的部分工程发包给具有相应资质条件的分包单位",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]