[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1114752":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1114752,788,1,"单选题","关于建筑工程的发包、承包方式，以下说法错误的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","建筑工程的发包方式分为招标发包和直接发包",false,{"key":16,"text":17,"correct":14},"B","未经发包方同意且无合同约定，承包方不得对专业工程进行分包",{"key":19,"text":20,"correct":14},"C","联合体各成员对承包合同的履行承包连带责任",{"key":22,"text":23,"correct":24},"D","发包方有权将单位工程的地基与基础、主体结构、屋面等工程分别发包给符合资质的施工单位",true,"2020版教材P97页 《建筑法》规定，建筑工程总承包单位可以将承包工程中的部分工程发包给具有相应资质条件的分包单位。禁止承包单位将其承包的全部建筑工程转包给他人，禁止承包单位将其承包的全部建筑工程肢解以后以分包的名义分别转包给他人。施工总承包的，建筑工程主体结构的施工必须由总承包单位自行完成。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]