[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1114726":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1114726,788,1,"单选题","对于全部使用国有资金的项目，建设单位将建设工程肢解发包的，下列有关法律责任的说法正确的是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","重新审批该项目",false,{"key":16,"text":17,"correct":14},"B","应当暂停项目执行",{"key":19,"text":20,"correct":14},"C","应当暂停资金拨付",{"key":22,"text":23,"correct":24},"D","责令改正，处以罚款",true,"2020版教材P80页 《建设工程质量管理条例》进一步规定，建设单位不得将建设工程肢解发包。建设单位将建设工程肢解发包的，责令改正，处工程合同价款0.5%以上1%以下的罚款；对全部或者部分使用国有资金的项目，并可以暂停项目执行或者暂停资金拨付。B、C选项错在应当两字，应该是并可以暂停项目执行或者暂停资金拨付。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]