[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1114713":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1114713,788,1,"单选题","根据《招标投标法》，投标人补充、修改或者撤回已提交的投标文件，并书面通知招标人的时间期限应在（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","评标截止时间前",false,{"key":16,"text":17,"correct":14},"B","评标开始前",{"key":19,"text":20,"correct":21},"C","提交投标文件的截止时间前",true,{"key":23,"text":24,"correct":14},"D","投标有效期内","2020版教材P82页 《招标投标法》规定，投标人在招标文件要求提交投标文件的截止时间前，可以补充、修改或者撤回已提交的投标文件，并书面通知招标人。补充、修改的内容为投标文件的组成部分",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]