[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1114694":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1114694,788,1,"单选题","某工程项目标底价是850万元人民币，投标时甲承包商根据自己企业定额算得成本是800万元人民币，乙承包商根据自己企业定额算得成本是700万元人民币。则甲承包商投标时报价不得低于()万元人民币。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","850",false,{"key":16,"text":17,"correct":14},"B","700",{"key":19,"text":20,"correct":14},"C","750",{"key":22,"text":23,"correct":24},"D","800",true,"2020版教材P85页 投标人不得以低于成本的报价竞标。而对于甲而言的成本价为800万元。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]