[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1114656":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1114656,788,1,"单选题","依据《建筑工程施工发包与承包计价管理办法》，下列关于标底与投标限价的说法，正确的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","国有资金投资的建筑工程，必须设有招标标底",false,{"key":16,"text":17,"correct":18},"B","国有资金投资的建筑工程招标，应当设有最高投标限价",true,{"key":20,"text":21,"correct":14},"C","非国有资金投资的建筑工程招标可设有最低投标限价",{"key":23,"text":24,"correct":14},"D","设有最高投标限价，应当在招标时保密","2020版教材P76页 招标人设有最高投标限价的，应当在招标时公布最高投标限价的总价，所以D错误。国有资金投资的建筑工程招标的，应当设有最高投标限价。非国有资金投资的建筑工程招标的，可以设有最高投标限价或者招标标底",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]