[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1114628":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1114628,788,1,"单选题","依法必须进行招标的项目提交资格预审申请文件的时间，自资格预审文件停止发售之日起不得少于()日。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","5",true,{"key":16,"text":17,"correct":18},"B","7",false,{"key":20,"text":21,"correct":18},"C","10",{"key":23,"text":24,"correct":18},"D","15","2020版教材P77页 招标人应当合理确定提交资格预审申请文件的时间。依法必须进行招标的项目提交资格预审申请文件的时间，自资格预审文件停止发售之日起不得少于5日。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]