[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1114496":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1114496,788,1,"单选题","承包单位将承包的工程转包的,对因转包工程不符合规定的质量标准造成的损失,由()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","接受转包的单位自行承担全部赔偿责任",false,{"key":16,"text":17,"correct":14},"B","承包单位自行承担全部赔偿责任",{"key":19,"text":20,"correct":14},"C","承包单位与接受转包的单位承担按份赔偿责任",{"key":22,"text":23,"correct":24},"D","承包单位与接受转包的单位承担连带赔偿责任",true,"2020版教材P61页 承包单位将承包的工程转包的,或者违反本法规定进行分包的,责令改正,没收违法所得,并处罚款,可以责令停业整顿,,降低资质等级;情节严重的,吊销资质证书。承包单位有以上规定的违法行为的,对因转包工程或者违法分包的工程不符合规定的质量标准造成的损失,与接受转包或者分包的单位承担连带赔偿责任。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]