[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1114468":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1114468,788,1,"单选题","某建设工程按规定于2012年6月1日办理了开工报告审批手续，但因故一直没有开工，同年12月7日准备开工时，建设单位应当（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","向发证机关申请延期",false,{"key":16,"text":17,"correct":14},"B","报批准机关核验开工报告",{"key":19,"text":20,"correct":21},"C","重新办理开工报告批准手续",true,{"key":23,"text":24,"correct":14},"D","改办施工许可证","2020版教材P49页 对于实行开工报告制度的建设工程，《建筑法》规定，按照国务院有关规定批准开工报告的建筑工程，因故不能按期开工或者中止施工的，应当及时向批准机关报告情况。因故不能按期开工超过6个月的，应当重新办理开工报告的批准手续。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]