[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1114467":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1114467,788,1,"单选题","建设工程施工许可证的申请主体是该工程的（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工单位",false,{"key":16,"text":17,"correct":18},"B","建设单位",true,{"key":20,"text":21,"correct":14},"C","监理单位",{"key":23,"text":24,"correct":14},"D","咨询服务单位","2020版教材P45页 建设单位是建设项目的投资者，为建设项目开工和施工单位进场做好各项前期准备工作，是建设单位应尽的义务。因此，施工许可证的申请领取，应该是由建设单位负责，而不是施工单位或者其他单位。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]