[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1114465":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1114465,788,1,"单选题","某房地产开发公司拟在某市旧城区一块地上开发住宅小区工程项目，建设工程合同价格为20000万元，工期为18个月，按照国家有关规定，该开发公司应当向工程所在地的区政府建设局申请领取施工许可证。申请领取施工许可证的时间最迟应当在（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","确定施工单位前",false,{"key":16,"text":17,"correct":18},"B","住宅小区工程开工前",true,{"key":20,"text":21,"correct":14},"C","确定监理单位前",{"key":23,"text":24,"correct":14},"D","住宅小区工程竣工验收前","2020版教材P43页 《建筑法》规定，建筑工程开工前，建设单位应当按照国家有关规定向工程所在地县级以上人民政府建设行政主管部门申请领取施工许可证。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]