[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1114463":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1114463,788,1,"单选题","甲建设单位2011年9月1日领取了施工许可证。由于特殊原因不能按期开工，故向发证机关申请延期。根据我国《建筑法》的规定，则关于延期的说法正确的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","可以延期，但只能延期一次",false,{"key":16,"text":17,"correct":14},"B","领取施工许可证延期次数不受限制",{"key":19,"text":20,"correct":14},"C","延期以两次为限，每次不超过两个月",{"key":22,"text":23,"correct":24},"D","超过延期时限的，施工许可证自行废止",true,"2020版教材P48页 《建筑法》规定，建设单位应当自领取施工许可证之日起3个月内开工。因故不能按期开工的，应当向发证机关申请延期；延期以两次为限，每次不超过3个月。既不开工又不申请延期或者超过延期时限的，施工许可证自行废止。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]