[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1114454":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1114454,788,1,"单选题","实行开工报告审批制度的建设工程，对开工报告审查的内容中与颁发施工许可证的工程不同的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","资金到位情况",false,{"key":16,"text":17,"correct":18},"B","投资项目市场预测情况",true,{"key":20,"text":21,"correct":14},"C","设计图纸是否满足施工要求",{"key":23,"text":24,"correct":14},"D","现场条件是否三通一平等","2020版教材P44页 开工报告审查的内容主要包括：(1)资金到位情况；(2)投资项目市场预测；(3)设计图纸是否满足施工要求；(4)现场条件是否具备“三通一平”等的要求。 施工许可证的法定批准条件（7）建设资金已经落实；（5）有满足施工需要的施工图纸及技术资料；《建筑工程施工许可管理办法》进一步规定，（3）施工场地已经基本具备施工条件；",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]