[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1114447":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1114447,788,1,"单选题","对于实行开工报告制度的建设工程，因故不能按期开工超过6个月的，应当()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","申请延期开工",false,{"key":16,"text":17,"correct":14},"B","重新核验",{"key":19,"text":20,"correct":21},"C","重新办理批准手续",true,{"key":23,"text":24,"correct":14},"D","备案","2020版教材P49页 三、重新办理批准手续的规定对于实行开工报告制度的建设工程，《建筑法》规定，按照国务院有关规定批准开工报告的建筑工程，因故不能按期开工或者中止施工的，应当及时向批准机关报告情况。因故不能按期开工超过6个月的，应当重新办理开工报告的批准手续。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]