[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1114445":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1114445,788,1,"单选题","某建设单位领取了施工许可证，因故不能在3个月内开工，但又未申请延期。该施工许可证()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","自行废止",true,{"key":16,"text":17,"correct":18},"B","重新核验",false,{"key":20,"text":21,"correct":18},"C","继续有效",{"key":23,"text":24,"correct":18},"D","自动延期","2020版教材P48页 《建筑法》规定，建设单位应当自领取施工许可证之日起3个月内开工。因故不能按期开工的，应当向发证机关申请延期；延期以两次为限，每次不超过3个月。既不开工又不申请延期或者超过延期时限的，施工许可证自行废止。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]