[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1114435":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1114435,788,1,"单选题","下列选项中，符合《建筑法》有关施工许可证规定的说法或做法的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","为争取早日竣工，建设单位可先行开工建设，但最迟应该在开工后1个月内申请补办施工许可证",false,{"key":16,"text":17,"correct":14},"B","开工前，建设单位可申请延期办理施工许可证，延期至多允许3个月",{"key":19,"text":20,"correct":14},"C","取得施工许可证后，工程未按期开工的，该施工许可证将在3个月后自行废止",{"key":22,"text":23,"correct":24},"D","取得施工许可证后，工程因故中止，建设单位在一个月内向发证机关递交了报告",true,"2020版教材P48页 《建筑法》规定，在建的建筑工程因故中止施工的，建设单位应当自中止施工之日起一个月内，向发证机关报告，并按照规定做好建筑工程的维护管理工作。建筑工程恢复施工时，应当向发证机关报告；中止施工满一年的工程恢复施工前，建设单位应当报发证机关核验施工许可证。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]