[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1114351":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1114351,788,1,"单选题","某工程项目工期计划为 18个月，其中合同价款中安全防护、文明施工措施费用为86万元，在合同没有约定或约定不明情况下，建设单位预付该部分费用至少应为（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","25.8万",true,{"key":16,"text":17,"correct":18},"B","34.4万",false,{"key":20,"text":21,"correct":18},"C","43万",{"key":23,"text":24,"correct":18},"D","51.6万","《建筑工程安全防护、文明施工措施费用及使用管理规定》中规定，建设单位与施工单位在施工合同中对安全防护、文明施工措施费用预付、支付计划未作约定或约定不明的，合同工期在一年以内的，建设单位预付安全防护、文明施工措施项目费用不得低于该费用总额的 50%；合同工期在一年以上的（含一年），预付安全防护、文明施工措施费用不得低于该费用总额的30%，其余费用应当按照施工进度支付。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]