[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1114350":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1114350,788,1,"单选题","监理工程师发现设计文件存在严重问题，下令施工现场停工，如合同中无明确约定，则停工产生的一系列费用应由（ ）承担。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工单位",false,{"key":16,"text":17,"correct":18},"B","建设单位",true,{"key":20,"text":21,"correct":14},"C","设计单位",{"key":23,"text":24,"correct":14},"D","监理单位","本题考查的是施工现场安全防护。费用由责任方承担，这里指的责任方是施工合同的某一方，并非真正的责任者。设计单位的责任，先由建设单位承担，再由建设单位根据设计合同追偿。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]