[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1114311":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1114311,788,1,"单选题","在城市市区内，可能产生噪声污染的工程项目，施工单位应当在工程开工前（ ）天，向环境保护行政主管部门申报。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","3",false,{"key":16,"text":17,"correct":14},"B","7",{"key":19,"text":20,"correct":21},"C","15",true,{"key":23,"text":24,"correct":14},"D","28","本题考查的是施工现场环境噪声污染的防治。《环境噪声污染防治法》规定，在城市市区范围内，建筑施工过程可能产生噪声污染，施工单位须在开工15日以前向所在地县级以上环境行政主管部门申报该工程采取的环境噪声污染防治情况。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]