[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1114308":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1114308,788,1,"单选题","城市道桥、铁路、工业厂房等建设项目，在建成后使用过程中可能会对周围环境产生噪声污染，因此、建设单位在（ ）就须依法规定防治措施，并同步建设环境噪声污染防治设施。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建设前期",true,{"key":16,"text":17,"correct":18},"B","建设过程中",false,{"key":20,"text":21,"correct":18},"C","建设后期",{"key":23,"text":24,"correct":18},"D","使用过程中","本题考查的是建设项目噪声污染的防治。城市道桥、铁路、工业厂房等建设项目，在建成后使用过程中可能会对周围环境产生噪声污染，因此，建设单位在建设前期就须依法规定防治措施，并同步建设环境噪声污染防治设施。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]