[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1114288":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1114288,788,1,"单选题","经定作人同意，承揽人将其承揽的主要工作交由第三人完成。关于责任承担的说法，正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","第三人就完成的工作成果向定作人负责",false,{"key":16,"text":17,"correct":14},"B","承揽人不再承担责任",{"key":19,"text":20,"correct":14},"C","承揽人与第三人按完成工作成果的比例向定作人承担责任",{"key":22,"text":23,"correct":24},"D","承揽人就该第三人完成的工作成果向定作人负责",true,"本题考查的是承揽合同的特征。承揽人就第三人完成的工作成果向定作人负责。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]