[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1114256":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1114256,788,1,"单选题","某建设工程施工过程中，由于材料价格涨幅较大，施工企业项目经理与建设单位的现场代表多次协商调整材料价格，但未确定最终结算价格。在协商过程中，建设单位更换了现场代表。关于该施工合同的变更，下列说法正确的是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","由于建设单位的现场代表变动，该合同视为无效",false,{"key":16,"text":17,"correct":14},"B","由于建设单位的现场代表变动，该合同视为未变更",{"key":19,"text":20,"correct":21},"C","双方对材料价格变更的内容约定不明确，推定为未变更",true,{"key":23,"text":24,"correct":14},"D","双方对材料价格变更的内容约定不明确，推定按市场价格变更","现场代表变动属于合同主体（当事人）变更。《民法典》规定，合同变更内容约定不明，推定为未变更。“材料价格变更”属于合同内容变更，约定不明，推定为未变更。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]