[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1114242":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1114242,788,1,"单选题","承包人实施工程师的处理意见后，可书面提出复工要求，工程师未能在（ ）答复的，承包人可自行复工。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","12h",false,{"key":16,"text":17,"correct":14},"B","24h",{"key":19,"text":20,"correct":14},"C","36h",{"key":22,"text":23,"correct":24},"D","48h",true,"本题考查的是建设工程工期。承包人实施工程师的处理意见后，可书面提出复工要求，工程师应在48小时内给予答复，未48小时答复的，承包人可自行复工。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]