[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1114236":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1114236,788,1,"单选题","建设工程施工合同约定，施工企业未按节点工期完成约定进度的工程单位可解除合同，此约定属于合同的（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","附期限解除",false,{"key":16,"text":17,"correct":18},"B","附条件解除",true,{"key":20,"text":21,"correct":14},"C","附期限终止",{"key":23,"text":24,"correct":14},"D","附条件终止","本题考查的是合同的终止。首先，应当明确如何区别所附为“条件”或为“期限”。若所附为“条件”，则该“条件”可能成就也可能不成就，而若所附为“期限”，则该“期限”必然会到来。从题目上看，“…施工企业未按节点工期完成形象进度的…”，很明显，施工企业可能按节点工期完成进度，也可能未完成，故其所附为“条件”；而后续描述“建设单位可以解除合同”，故，此为附解除条件的合同。选项B正确。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]