[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1114220":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1114220,788,1,"单选题","甲乙双方的施工合同约定工程应于2013年5月10日竣工，但是乙方因为管理不善导致工程拖期，在5月20日到5月25日该地区发生洪灾，造成工期一再拖延，最后竣工时间为2013年5月31日。甲方在支付乙方工程费用时，拟按照合同约定扣除因乙方工程拖期的违约费用，那么甲方应该计算（ ）天的拖期违约损失。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","15",false,{"key":16,"text":17,"correct":14},"B","16",{"key":19,"text":20,"correct":14},"C","17",{"key":22,"text":23,"correct":24},"D","21",true,"本题考查的是违约责任及违约责任的免除。当事人迟延履行后发生不可抗力的，不能免除责任。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]