[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1114173":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1114173,788,1,"单选题","招标人应当自确定中标人之日起（ ）日内，向有关行政监督部门提交招标投标情况书面报告。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","15",true,{"key":16,"text":17,"correct":18},"B","10",false,{"key":20,"text":21,"correct":18},"C","20",{"key":23,"text":24,"correct":18},"D","5","本题考查的是中标的法定要求和招标投标投诉处理。招标人应当自确定中标人之日起15日内，向有关行政监督部门提交招标投标情况书面报告。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]