[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1114161":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1114161,788,1,"单选题","下列关于建筑工程施工许可的表述，不正确的有（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建设单位应当自领取施工许可证之日起40天内开工",true,{"key":16,"text":17,"correct":18},"B","工程因故中止施工，建设单位应在中止施工之日起1个月内向原发证机关报告",false,{"key":20,"text":21,"correct":18},"C","中止施工满1年的工程恢复施工前，应重新核验施工许可证",{"key":23,"text":24,"correct":18},"D","因故不能在领取施工许可证后的3个月内开工时，应当申请延期","《建筑法》规定，建设单位应当自领取施工许可证之日起 3个月内开工。因故不能按期开工的，应当向发证机关申请延期；延期以两次为限，每次不超过3个月。既不开工又不申请延期或者超过延期时限的，施工许可证自行废止。 @##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]