[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1114159":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1114159,788,1,"单选题","某建设单位于2018年2月1日领取施工许可证，由于某种原因工程未能按期开工，该建设单位按照《建筑法》规定向发证机关申请延期，该工程最迟应当在（ ）开工。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","2018年3月1日",false,{"key":16,"text":17,"correct":14},"B","2018年5月1日",{"key":19,"text":20,"correct":14},"C","2018年8月1日",{"key":22,"text":23,"correct":24},"D","2018年11月1日",true,"本题考查的是施工许可证延期开工、核验和重新办理批准的规定。《建筑法》规定，建设单位应当自领取施工许可证之日起3个月内开工。因故不能按期开工的，应当向发证机关申请延期；延期以两次为限，每次不超过3个月。既不开工又不申请延期或者超过延期时限的，施工许可证自行废止。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]