[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1114157":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1114157,788,1,"单选题","某工程开工后3个月因故中止施工，建设单位应该履行的合法手续（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","向发证机关申请延期",false,{"key":16,"text":17,"correct":18},"B","自中止施工之日起一个月内，向发证机关报告",true,{"key":20,"text":21,"correct":14},"C","自中止施工之日起一个月内，报发证机关核验施工许证",{"key":23,"text":24,"correct":14},"D","向发证机关申请施工许可证废止","《建筑法》规定，在建的建筑工程因故中止施工的，建设单位应当自中止施工之日起一个月内，向发证机关报告，并按照规定做好建筑工程的维护管理工作。A错，只有在建设工程因故不能按期开工时，建设单位才应当项发证机关申请延期；C项，建筑工程施工满1年的工程恢复施工前，建设单位应当报发证机关核验施工许可证。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]