[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1114143":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1114143,788,1,"单选题","关于安装工程一切险保险期限的说法，正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","安装期保险期限的起始或终止可以超出保险单明细表中列明的保险生效日或终止日",false,{"key":16,"text":17,"correct":14},"B","安装工程一切险对旧机械设备不负考核期的保险责任，但需承担起维修期的保险责任",{"key":19,"text":20,"correct":14},"C","安装工程一切险的保险期内一般应包括一个试车考核期，试车考核期的长短可以超出安装工程保险单明细表中列明的试车和考核期限",{"key":22,"text":23,"correct":24},"D","安装工程一切险的保险责任自保险工程在工地动工或用于保险工程的材料、设备运抵工地之时起始",true,"本题考查的是安装工程一切险及第三者责任险。选项A，在任何情况下，安装期保险期限的起始或终止不得超出保险单明细表中列明的保险生效日或终止日；选项B、C，安装工程一切险对于旧机器设备不负考核期的保险责任，也不承担其维修期的保险责任；试车考核期的长短一般根据安装工程合同中的约定进行确定，但不得超出安装工程保险单明细表中列明的试车和考核期限。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程法规及相关知识","建筑工程",0]