[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1114060":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1114060,787,2,"多选题","工业安装工程完毕后，建设单位应组织（）参加单位工程质量验收。2014",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","建设制造单位",false,{"key":16,"text":17,"correct":18},"B","施工单位",true,{"key":20,"text":21,"correct":18},"C","设计单位",{"key":23,"text":24,"correct":14},"D","材料供应单位",{"key":26,"text":27,"correct":18},"E","质量监督站","BCE","考查内容：建筑安装工程施工质量验收统一要求单位工程完工后，由施工单位向建设单位提出报验申请，由建设单位负责人组织施工单位、监理单位、设计单位、质量监督部门等项目负责人进行验收。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]