[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1114054":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1114054,787,2,"多选题","关于工程竣工档案编制及移交的要求，正确的有（）。2017",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","项目竣工档案一般不少于两套",true,{"key":16,"text":17,"correct":18},"B","档案资料原件由建设单位保管",false,{"key":20,"text":21,"correct":14},"C","应编制工程档案资料移交清单",{"key":23,"text":24,"correct":14},"D","双方应在应缴清单上签字盖章",{"key":26,"text":27,"correct":18},"E","档案资料移交清单需一式三份","ACD","本题考查的是几点工程项目竣工档案管理要求。选项B，原件是由承建档案馆来保存的；选项E，档案资料移交清单一式两份。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]