[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1114050":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1114050,787,2,"多选题","工程项目索赔发生的原因中，属于不可抗力因素的有（）。2018",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","台风",true,{"key":16,"text":17,"correct":18},"B","物价变化",false,{"key":20,"text":21,"correct":14},"C","地震",{"key":23,"text":24,"correct":14},"D","洪水",{"key":26,"text":27,"correct":14},"E","战争","ACDE","机电工程项目索赔发生的原因 （1）合同对方违约。不履行或未能正确履行合同义务与责任。 （2）合同条文问题。合同条文不全、错误、矛盾，设计图纸、技术规范错误等。 （3）合同变更。 （4）工程环境变化。包括法律、物价和自然条件的变化等。 （5）不可抗力因素。如恶劣气候条件、地震、洪水、战争状态等。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]