[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1114043":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1114043,787,2,"多选题","下列施工作业内容中，需要编制施工方案的有（）。2017",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","大型设备吊装",true,{"key":16,"text":17,"correct":18},"B","支架制作安装",false,{"key":20,"text":21,"correct":14},"C","压力管道焊接",{"key":23,"text":24,"correct":14},"D","设备试运行",{"key":26,"text":27,"correct":18},"E","灯具安装接线","ACD","本题考查的事编制主要施工方案。针对制约施工进度的关键工序和质量控制的重点分项工程，编制主要施工方案。例如，大型设备起重吊装方案、调试方案、重要焊接方案、设备试运行方案等。【教材内容已删除】",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]