[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1114028":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1114028,787,2,"多选题","通风与空调施工中，安装单位应承担的协调配合工作有（）2013",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","向设备供应商提供设备到货时间",true,{"key":16,"text":17,"correct":18},"B","与装饰单位协调风口开设位置",false,{"key":20,"text":21,"correct":14},"C","向电气单位提供设备的电气参数",{"key":23,"text":24,"correct":18},"D","复核及整改土建施工完毕的预留孔洞尺寸",{"key":26,"text":27,"correct":18},"E","负责各机电专业管线综合布置的确定","AC","通风与空调工程施工中应注意与土建工程.装饰装修工程、机电安装其他专业工程以及设备供应商的协调配合。例如：配合土建预留、预埋时，注意预留孔、洞的形状、尺寸及位置，预埋件的尺寸和位置等；各类管线的综合布置及施工顺序的确定；及时为电气专业提供有关设备的电气参数、控制点及控制要求等数据；安装风机盘管、风口（包括送、回风口及新风入口等）及开设检修门时，注意对装饰装修工程的成品保护；及时向设备供应商提供设备到货时间、安装要求及相应数据等。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]