[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1114026":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1114026,787,2,"多选题","风管制作安装完成后必须对风管的（）进行严密性检验。2012",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","板材",false,{"key":16,"text":17,"correct":18},"B","咬口缝",true,{"key":20,"text":21,"correct":18},"C","铆接孔",{"key":23,"text":24,"correct":18},"D","法兰翻边",{"key":26,"text":27,"correct":18},"E","管段接缝","BCDE","考查内容：通风与空调工程施工程序。 风管安装完后，必须对进行严密性试验，主要检验风管、部件制作加工后的咬口缝、铆接孔，风管的法兰翻边、风管段之间接缝的严密性，检验以主、干管为主，检验合格后方能交付下道工序。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]