[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1114022":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1114022,787,2,"多选题","关于通风与空调系统进行试运行与调试的说法，正确的有（）。2017",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","设备单机试运转前进行口头安全技术交底",false,{"key":16,"text":17,"correct":18},"B","通风系统的联系试运行应不少于2h",true,{"key":20,"text":21,"correct":18},"C","空调系统带冷（热）源的连续运行运行应不少于8h",{"key":23,"text":24,"correct":18},"D","系统总风量实测值与设计风量的偏差允许值不应大于10%",{"key":26,"text":27,"correct":18},"E","空调冷（热）水总流量测试结果与设计流量的偏差不应大于10%","BCDE","本题考查的是通风与空调工程的施工程序。选项A，设备单机试运转安全保证措施要齐全、可靠，并有书面的安全技术交底。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]