[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1114010":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1114010,787,2,"多选题","下列室内配线施工中，属于镀锌钢管明配的工序有（）2014",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","测量定位",true,{"key":16,"text":17,"correct":14},"B","支架安装",{"key":19,"text":20,"correct":21},"C","钢管预埋",false,{"key":23,"text":24,"correct":14},"D","钢管连接",{"key":26,"text":27,"correct":21},"E","管内穿线","ABD","室内配线的施工程序中，明配管施工程序：测量定位→支架制作、安装→导管预制→导管连接→接地线跨接→刷漆。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]