[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1114002":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1114002,787,2,"多选题","高层住宅给水排水及室内雨水管道应在（）后，再穿外墙做出户管道。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","室内管道安装",false,{"key":16,"text":17,"correct":14},"B","室内管道试压",{"key":19,"text":20,"correct":14},"C","室内管道防腐施工",{"key":22,"text":23,"correct":24},"D","结构封顶",true,{"key":26,"text":27,"correct":24},"E","初沉降","DE","安装给水排水及室内雨水管道时，应在结构封顶并经初沉后进行施工。高层住宅因高度大，层数多，沉降量大，要避免出地下室的管道承受沉降的剪力而损坏。如果因赶工需要同步进行安装，则应先安装建筑物内的管道，等结构封顶初沉后再穿外墙做出户管道。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]