[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113992":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113992,787,2,"多选题","下列奥氏体不锈钢立式储罐绝热施工顺序的描述中，正确的有（）。2016",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","焊接在罐体上的绝热层固定件，应在罐体绝热施工前完成",true,{"key":16,"text":17,"correct":14},"B","储罐气密性试验合格后，进行绝热施工",{"key":19,"text":20,"correct":21},"C","储罐绝热施工完成后，整罐进行水压试验",false,{"key":23,"text":24,"correct":14},"D","储罐外表面已按要求进行铝箔隔离才能进行绝热层施工",{"key":26,"text":27,"correct":21},"E","储罐绝热施工完成后才能进行储罐上仪表的接管工作","ABD","本题考查的是绝热工程施工准备。 1）设备或管道应做水压试验.气密性试验并合格。 2）各种支架、支座、吊架、热工仪表等接管应安装完毕且符合设计要求。 3）对设备和管道安装中焊接、防腐等工序办理工序交接手续，设备和管道进行表面预处理。 4）在有防腐、衬里的设备及管道上焊接绝热层的固定件时，焊接及焊后热处理必须在防腐、衬里和试压之前进行。 5）奥氏体不锈钢设备或管道绝热施工前宜根据设计或图纸要求对其采用油漆或铝箔进行隔离防腐。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]