[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113979":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113979,787,2,"多选题","锅炉组件吊装原则有（）。2012",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","先上后下",true,{"key":16,"text":17,"correct":18},"B","先小件后大件",false,{"key":20,"text":21,"correct":14},"C","先两侧后中间",{"key":23,"text":24,"correct":14},"D","先中心再炉前炉后",{"key":26,"text":27,"correct":18},"E","先外围后内部","ACD","考查内容：锅炉设备安装技术。锅炉组件吊装的原则：先上后下，先两侧后中间，先中间再逐渐炉前、炉后进行。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]