[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113972":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113972,787,2,"多选题","关于管道系统压力试验前应具备条件的说法，正确的有（）。2017",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","管道上的膨胀节已设置了临时约束装置",true,{"key":16,"text":17,"correct":18},"B","管道防腐及绝热工程已全部结束",false,{"key":20,"text":21,"correct":14},"C","符合压力试验要求的液体或气体已经备齐",{"key":23,"text":24,"correct":14},"D","试验方案已经过批准，并已进行安全交底",{"key":26,"text":27,"correct":18},"E","至少有1块在周检期内检验合格的压力表","ACD","本题考查的是管道系统试验。选项B，试验范围内的管道安装工程在防腐.绝热之后；选项E，压力表不得少于两块。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]