[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1113971":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1113971,787,2,"多选题","工业管道系统泄漏性试验的正确实施要点有（）。2016",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","泄漏性试验的试验介质宜采用空气",true,{"key":16,"text":17,"correct":18},"B","试验压力为设计压力的1.5倍",false,{"key":20,"text":21,"correct":18},"C","泄漏性试验应在压力试验前进行",{"key":23,"text":24,"correct":14},"D","泄漏性试验可结合试车一并进行",{"key":26,"text":27,"correct":14},"E","输送极度和高度危害介质的管道必须进行泄漏性试验","ADE","本题考查的是工业管道系统泄漏性试验的实施要点。 1）输送极度和高度危害介质以及可燃介质的管道.必须进行泄漏性试验。 2）泄漏性试验应在压力试验合格后进行，试验介质宜采用空气。 3）泄漏性试验压力为设计压力。 4）泄漏性试验可结合试车一并进行。",{"id":6,"name":31,"category":32,"favorite":33},"二建机电工程实务","建筑工程",0]